Knowledge base
Casting and machining guides for engineers and buyers
These are the questions we answer every week — process selection, material choice, tolerances, lead times, tooling and paperwork — written down properly so you can use them whether or not you buy from us. Nothing here is a sales pitch. If a question is missing, ask it and we will add it.
Guides
Technical articles
Long-form guides written for the person who has to make the call: the design engineer choosing a process, or the buyer who has to explain a price difference to management.
Process selection
Investment casting vs sand casting: which process fits your part?
Tolerance, surface finish, minimum wall thickness, tooling cost and the volume range where each process wins — plus a decision checklist and the cases where neither process is the right answer.
Sourcing & RFQ
How to get an accurate casting quotation on the first try
Why quotes for the same drawing can differ by 40 percent, what to put in an RFQ so offers come back comparable, and the omissions that send a price up or a quotation straight into the bin.
Coming soon
How to choose between 304, 316 and 316L stainless steel
A practical corrosion and strength comparison for the three grades that cover most stainless castings, and how to avoid over-specifying a grade you do not need.
Coming soon
Understanding casting tolerance grades: ISO 8062 explained
What the CT grades actually mean, how the tolerance band scales with dimension, and how to specify a grade that is tight enough without paying for precision you will not use.
Coming soon
What to check before you approve a first article sample
A first-article inspection checklist: which dimensions matter, what the report should contain, and the process-capability questions worth asking before you release volume.
Ask a question
Not covered here? Send us the question.
If you are weighing a process, a material or a tolerance and cannot find a straight answer, put it to us. We answer technical questions from non-customers too.
Frequently asked questions
Selection, standards, lead time, tooling and paperwork
Straight answers, including where the honest answer is “it depends”. Where a figure is order-specific we say so rather than quote a number we cannot hold to.
Should I specify casting or machining for a new part?
Casting is the better route when the part has complex geometry, internal features or a shape that would waste a large amount of material if cut from bar stock. Machining from solid suits simple prismatic parts, parts with tight tolerances across the whole surface, and very low quantities where tooling cannot be justified. Many parts are a hybrid: cast close to net shape, then machine only the functional faces.
How do I choose between 304, 316 and 316L stainless steel?
304 is the general-purpose austenitic grade and the least expensive of the three; it is fine for fresh water and mild atmospheres but can suffer chloride pitting. 316 adds molybdenum and is the usual choice for marine hardware, chemical service and coastal locations. 316L is the low-carbon version of 316: it keeps the corrosion resistance through welding instead of forming chromium carbides at the weld line, so it is the grade we quote for welded and hygienic assemblies. Choose the lowest grade that meets your corrosion and strength requirement.
How do I read an ISO 8062 casting tolerance, and what standard should go on the drawing?
ISO 8062-3 assigns a cast tolerance grade from CT1 (finest) to CT16 (coarsest). Each grade defines a total tolerance band that grows with the nominal dimension. Our investment casting process holds ±0.1 mm by process, so a 100 mm dimension is quoted inside that band unless your drawing calls for something tighter or looser; a sand casting on the same dimension typically allows several times that. Put the grade you need on the drawing, and state the machining standard for finished surfaces (for example ISO 2768-m) so the foundry and the machinist work to the same numbers.
How long does a sample casting take?
Sampling takes 10 days from order, for both investment casting and lost foam. That window covers drawing review, wax die manufacture and the first sample casting with its dimensional report. Where a part needs a more complex die we tell you before you commit, rather than letting the date slip.
How long is production lead time after the sample is approved?
Production runs 25 days at MOQ 500 pcs, counted from sample approval and receipt of deposit, and that figure already includes casting, machining, heat treatment, finishing and inspection where the drawing calls for them. Repeat orders against existing tooling skip tooling and sampling entirely and go straight into that 25-day window.
Can you handle a rush order?
Yes, for most parts. We can compress the schedule by adding shifts on wax injection and shell building and by prioritising your heat in the melt shop. A rush surcharge applies and the achievable date depends on current load, so raise it early — expediting is far easier before the tooling is cut than after.
How are samples charged, and do you start production only after sample approval?
Samples are not free. The first castings carry the tooling cost plus a sample charge, both confirmed in the quotation before anything is made. We do not begin series production until you approve the sample in writing, so you never pay for volume you have not accepted.
What is your minimum order quantity, and can I place a trial order?
Series production starts at 500 pcs per part number, and trial or prototype batches below that are quoted as tooling trials. If you need a small trial order before committing to a forecast, say so in the RFQ. Running a small batch to prove the part is better than ordering volume against an unproven design.
Who pays for the tooling, who owns it, and can it be transferred?
Wax dies and machining fixtures are quoted as a separate line item. Once paid for, the tooling is your property. We hold and maintain it for your repeat orders, or release and ship it to you or to another supplier on written request. State your tooling ownership requirement in the RFQ so it is recorded from the start.
Will you sign an NDA for my drawings?
Yes. We sign non-disclosure agreements and return them before you release drawings. If you prefer, send a watermarked 2D drawing for the initial quotation and release the full 3D model only after the NDA is in place.
What quality documents do you provide, and can you arrange third-party inspection?
The documentation set is agreed at order stage: a material certificate traceable to the heat number, a dimensional report and the first article inspection report are the usual set. Where your drawing calls for it, we arrange radiographic, ultrasonic, magnetic particle or dye penetrant testing and issue the report against your order reference. Third-party inspectors such as SGS, BV or TÜV, or your nominated agent, are welcome on site.
What are your payment and trade terms?
Payment is by T/T, with the deposit and balance ratio agreed in the quotation. We quote EXW or FOB, and other terms can be agreed to match your logistics. Terms are reviewed after the first few orders.
Are you a factory or a trading company?
We are a manufacturer, not a trading company. Casting, CNC machining, heat treatment, finishing and inspection all happen on our own site in Qingzhou, Shandong, and we retain the melt, heat-treatment and inspection records for the parts we ship. We are happy to arrange a video walkthrough or a factory visit before your first order.
Get the capability handbook as a PDF
Tolerance tables, material cross-references, weight and size ranges, finishing options and the RFQ checklist in one document you can forward internally or attach to an enquiry.
Still have a question the FAQ does not cover?
Send it with the drawing or on its own. You will get a written answer from the people who make the parts — and if the right answer is that you need a different process, we will tell you.